Inching Toward the Finish Line

As anticipated the November 1 closing date has come and gone without the house being ready.  We’ve signed an amendment to extend the deadline, but it’s still going to be tight to get everything done.  The hubs and I went to sand the sub floor in preparation for installing the flooring on Saturday, but found painting and cabinet installation in full swing when we arrived, so we weren’t able to get anything done.  We did unload the half order of flooring the vendor had in stock so it could acclimate on site for the recommended two days.  The remainder should arrive tomorrow or Tuesday, so we’ll have to let that acclimate on site as well before installing it.

Flooring

We had a meeting with the foreman and the realtors today to go over the timeline for the new closing date of December 1.  We will work on the flooring every evening this week, and the master bathroom tile should be installed in the next few days so we can finish flooring around that at the end.  Then the following week all of the finish work will be done – trim, doors, electrical outlets, paint touch up, etc.  The should put us at 95% complete for the appraisal the week before Thanksgiving.

The power line has finally been installed, so there is electric to the house now.  They ended up having to take a few more trees out at the end of the driveway to run the line, but getting power to the house is worth it.

2

1

You can see the small green box to the side of the house.  That’s our electrical pedestal.  That side of the house is getting pretty crowded with pips and utility features, so I’ll have to figure out some landscaping beyond my rain garden (which will have a retaining wall made from those tires) to hide them next season.

Inside, things are finally starting to look like the finished vision we’ve had all along.  The cabinets look great with the paint color and the tile coordinates perfectly as well.  Hopefully I’ll have pictures of that later this week, once it’s installed.

Kitchen

Kitchen2

Bath2

Bath

The counter tops are on-site and ready to be installed once the final tweaks are done on the cabinets.

Counters

I tested out the flooring next to the cabinets just to get a feel for it, and I’m pretty happy – even with the dusty paw prints!  I plan to attempt documenting the install over the course of the week and share that, so stay tuned!

Floor

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s